Project Progress

Official start of the project: 1st October 2012

Kick-off meeting – 15th November 2012 – INFINEON Premises - Munich Germany.

The objectives of the KO meeting were to present the technic and management overview of the project, its organisation and communication rules and a plan for the next 12 months

1st Review Meeting - 3rd December 2013 - EC premises - Brussels, Belgium

The Publishable Summary for Period 1 can be downloaded here

21M meeting– 25th June 2014 – ALMA CG Premises - Lyon, France.

Joint meeting DOT7 / RF2THz project - 26th June 2014 - Crolles, France

General Assembly Meeting - 25th March 2015 - BUW Campus - Wuppertal, Germany

2nd Review Meeting - 26th March - BUW campus - Wuppertal, Germany

The 2nd Publishable Summary can be downloaded here

Final Review meeting - 12th September 2016 - INFINEON premises - Munich - Germany